GoodEarth Umang Completes 15th Slab

By :
GoodEarth
 | Published on :
May 12, 2026

It is our pleasure to inform the completion of 15th Slab of Umang. Other works are also progressing steadily across the project. Brick work is currently ongoing on the 12th floor and is scheduled for completion next week. Plastering work on the 9th floor is nearing completion and is expected to finish this week. Electrical conduiting activities are in progress on the 11th floor, while plumbing work continues on the 6th floor. Putty work under the painting scope is ongoing on the 5th floor. Waterproofing activities are progressing on the 8th floor, and handrail installation work is currently underway on the 10th floor.

The project continues to advance as planned, with multiple activities progressing simultaneously to maintain construction momentum despite challenges posed by West Asian geo political situation and migrant labour returns.