Umang Completes 13th Slab

By :
GoodEarth
 | Published on :
March 11, 2026

We are pleased to share that construction at Good Earth Umang has successfully reached Stage 13, with multiple activities progressing steadily across different floors.

Current on-site progress includes:

Construction Progress Status
Category Current Status
Brick Work Ongoing on the 10th floor.
Plastering 7th floor finishing this week.
Electrical Conduiting Ongoing on the 8th floor
Plumbing Works Ongoing on the 4th floor
Handrail Installation Ongoing on the 7th floor.
Painting (Putty work) Ongoing on the 4th floor
Waterproofing Ongoing on the 5th floor.

Our projects team continue to work diligently to maintain quality and timely progress. We will keep you updated as the project advances further.