Good Earth Umang Completes 12th Slab

By :
GoodEarth
 | Published on :
February 24, 2026

We’re delighted to share the latest construction progress at Good Earth Umang. The project continues to move ahead at a steady pace, with significant milestones achieved across structural, masonry, and finishing works.

Brickwork has now been completed up to the 9th floor. This advancement gives clearer definition to the apartment layouts and internal spaces, bringing the structure closer to its finished look.

At a Glance: Current Milestones

Milestone Status

Construction Progress Status
Category Current Status
Structure Slab 12th Floor Completed.
Plastering Completed up to the 6th floor, enhancing wall finishes and preparing surfaces for the next stages of work.
Electrical Works Conduiting is finished up to the 7th floor
Plumbing Works Actively ongoing on the 3rd floor
Finishing & Safety Handrails Handrail installation is ongoing on the 6th floor.
Painting Work Painting (Putty work) is also underway on the 3rd floor, smoothing wall surfaces in preparation for final paint application.
Waterproofing Waterproofing work is in progress on the 4th floor.

With structural construction moving upward and finishing works progressing floor by floor, the vision of Good Earth Umang is steadily transforming into reality. Our team remains committed to maintaining high-quality standards, safety protocols, and timely execution at every stage.

We appreciate your continued trust and support. Stay tuned for the next update as we move closer to delivering your future home!