Good Earth Umang Construction Update: 9th Slab Completed

By :
GoodEarth
 | Published on :
December 12, 2025

The vertical structure continues to climb successfully!

Main Structure: The apartment structure has successfully completed the 9th floor slab.

Brickwork: Brickwork is currently in full swing on the 6th floor, shaping the individual homes and defining the spaces within.

Other Works: Essential internal activities are progressing steadily on the lower floors.Electrical Conduit & Wiring: Installation of electrical conduits and preliminary wiring is underway on the 3rd floor.

Plastering & Ceiling Works: Finishing works have begun from lower floors. Plastering and ceiling putty works have commenced on the 2nd floor, bringing smooth walls and ceilings to life.

We are dedicated to maintaining this pace while adhering to the highest standards of quality and safety. Thank you for being a part of the Good Earth Umang family!