Malhar Ochre - Updates June,25

June 17, 2025

Project progress this month

  • 60% of the compound wall construction has been completed for Plots 18 to 22 and Plots 28 to 33.
  • Plinth beam work is fully completed for Plots 2–6 and 34–37. Plot 18 is 80% done, while Plots 19–21 have reached 30% completion.
  • Ground floor lintel and slab work has commenced. Plots 4 to 6 have reached 50% completion for both GF lintel and slab.

Drone’s Eye View

Here’s a quick aerial view.

360° View

Explore the site from wherever youare – here’s a 360° glimpse of where it all begins.

A Quick Word from our Projects Team

"I coordinate people, materials, vehicles, and safety to work together smoothly."
- ABRAHAM MATHEW
Construction Manager

What’s Next

The remaining plots are scheduled next for the plinth beam activity. Additionally, the pile cap work and ground floor slab casting are in progress.