The foundation work for Blocks D to J has been completed, and the soil filling has also been carried out.
Excavation and levelling for Blocks C and K have been completed, and the foundation work is currently in progress.


In the upcoming month, excavation and levelling work for Blocks A, B, L, and M will be in progress.
Meanwhile, partial foundation work will commence for Blocks C and K, and the lower basement slab work is expected to begin by the end of April.